How Do I Replace a Fuse
NOTE:
The fuse inside the Energy Storage Module cannot be replaced separately. This
section describes how to replace the fuse of the Energy Storage Control Unit.
Prerequisite for replacing the fuse: If the inverter is faulty, the fuse is likely
to be damaged. In this case, check whether the fuse is damaged. If yes, replace the
fuse.
Step 1
Before the replacement, power off the system. >
Step 2
Loosen the screws on the fuse enclosure. >
Step 3
Open the fuse box, remove the fuse, insert a new fuse into the slot, and close
the fuse box. If you hear a click and the raised dots on the sides snap into the
box, the fuse is properly installed. >
-
How Often Do I Charge a Battery in Storage?
Do not store batteries for extended periods of time. The deep discharge during
storage may damage batteries. If you have to store batteries, observe the following
storage requirements.
Table 1-3 Lithium battery charge intervals >
-
Delayed Upgrade Description
After logging in to the inverter, if the FusionSolar app detects that the LUNA2000
firmware version is outdated, the app prompts you to upgrade the LUNA2000. You can
choose immediate activation or delayed activation. If you choose immediate
activation, the LUNA will be upgraded immediately after the firmware package is
uploaded. If you choose delayed activation, the activation of the firmware will be
performed four hours after you log out of the app.
-
How Do I Recycle Used Batteries?
NOTICE
- The Company does not recycle batteries. Contact local recycling agencies to handle
batteries.
- If there are no such agencies in your area, you can contact the nearest foreign
recycling agencies.
Step 1
Contact the nearest recycling agency.
Step 2
Recycling agencies assess the costs.
Step 3
Recycling agencies carry out recycling, which can be done in two
ways: >
Step 4
Recycling companies handle recycling. The recycled lithium batteries are at the
disposal of the recycling companies.
-
Baud Rate Negotiation
• The baud rate of MB0 series inverter is 115200, that of the M1 series inverter is
9600, and the default baud rate of S1 is "9600". When S1 is connected to
SUN2000-(12K-25K)-MB0, its baud rate will be automatically increased to 115200, so
the S1's baud rate needs to be restored to 9600 before powering off the system,
otherwise, the baud rate of S1 remains unchanged as 115200, and when using it with
the M1 inverter, the baud rate will show inconsistent leading to communication
failure.
• Steps: Use the Huawei FusionSolar App to scan the QR code to connect to the
inverter, go to the Communication Configuration page, and select RS485 > Baud Rate
Negotiation > RS485_2 > Baud Rate Negotiation > Restore to 9600.