Southeast Asia's First: Huawei Smart String Grid Forming ESS Completes GWh-Scale Black Start with Load — Grid Restoration and Islanded Operation Tests Pass Simultaneously

In the wave of building new-type power systems, grid-forming energy storage technology is advancing from an optional configuration to core infrastructure. On September 27, 2026 in Cambodia, the Huawei Smart String Grid Forming ESS successfully completed Southeast Asia's first GWh-scale Black Start with Load and Islanded Operation Capability Test, delivering an outstanding result for the project owner and developer SchneiTec and national grid operator Electricité du Cambodge (EDC).

Southeast Asia's First: Huawei Smart String Grid-Forming ESS Completes GWh-Scale Black Start with Load — Grid Restoration and Islanded Operation Tests Pass Simultaneously

Pursat Province, Cambodia: a 500 MW / 1000 MWh energy storage plant equipped with Huawei Smart String Grid Forming ESS

Cambodia is strengthening grid resilience and expanding renewable integration. Grid-forming energy storage acts as a key enabling power source to support grid restoration.

Addressing the specific needs of Cambodia's power grid, Huawei Digital Power, together with SchneiTec's project team, achieved synchronous coordination of 2,520 PCS units through its Smart String Grid Forming ESS. Starting independently from zero voltage, the system established synchronous voltage across three transformers (cumulative capacity of 920 MVA) within 10 seconds, with voltage built up smoothly and no inrush current during this initial energization. The energy storage system, acting as the main power source, restored local microgrid supply, charged over 400 km of transmission lines segment by segment, drove and coordinated with 120 MW of PV and 120 MW of hydropower supplying more than 10 substations, re-energizing the test network covering four western provinces step by step in a planned validation coordinated with EDC.

This validation completed a five-dimensional end-to-end closed loop:

Handling Zero Voltage and High Inrush Currents — The system can start independently from zero voltage, establish synchronous voltage across multiple transformers (cumulative capacity of 920 MVA), while successfully withstanding heavy inrush current impacts without requiring soft-start workarounds.
Multi-Source and Load Coordination — The system drove and coordinated 120 MW of PV and 120 MW of hydropower generation, autonomously smoothing fluctuations to maintain voltage and frequency stability across the entire system under complex operating conditions (such as multi-transformer switching and load fluctuations).
Bulk Grid & Transmission Line Restoration — It successfully re-energized test networks covering four western provinces by charging over 400 km of transmission lines segment by segment and restoring more than 10 substations.
Islanded Operation — Stable off-grid operation under load maintained the frequency over the long term. The Automatic Generation Control (AGC) functionality enabled active power dispatch and frequency regulation in a closed loop.
Resynchronization and Reconnection — The islanded grid was precisely aligned with the main grid for reconnection.

The five-dimensional validation forms a complete chain: "black start → multi-source integration → system restoration → sustained islanded operation → grid reconnection". It marks a milestone breakthrough in which the Huawei Smart String Grid Forming ESS transcends from plant-level application to grid-level independent stability application. From the black start source, to energizing transmission lines and transformers, and onward to PV, hydropower, and load integration, the system achieved an engineering-level grid breakthrough. Under complex operating conditions including multi-transformer switching, hydropower synchronization, unconstrained PV generation, and load fluctuations, the system consistently maintained frequency stability. This represents a significant improvement in frequency control precision compared to traditional solutions. Bulk grid restoration and islanded operation tests passed simultaneously.

Huawei Digital Power, leveraging its pioneering Smart String Grid Forming ESS, has earned the high recognition and broad trust of customers through continuous technological innovation. The validation supports Cambodia's goals of greater grid resilience and renewable energy integration. Furthermore, the successful GWh-scale black start, system restoration, and sustained islanded operation tests in Cambodia demonstrate a proven and replicable engineering solution for large-scale renewable energy integration, elevate clean energy development, and inject strong momentum into the global energy transition.